US Data Center Construction Costs Jump 13% in 2026, More Than Double Global Rate
Construction costs for large-scale data centers in the U.S. climbed 13% year-over-year in 2026, more than twice the global rate, according to a new report from project management firm Turner &...
Construction costs for large-scale data centers in the U.S. climbed 13% year-over-year in 2026, more than twice the global rate, according to a new report from project management firm Turner & Townsend. The increase was roughly three times the ten-year average.
Demand for AI computing power outpaced both the supply of powered land and the labor needed to build, stretching timelines and raising risk for contractors. The report examined over 500 live or recently completed projects across 62 global markets and surveyed 400 industry experts.
Paul Barry, Turner & Townsend's North America data center lead, said tighter schedules push contractors and subcontractors to build more risk allowances into their pricing - through acceleration allowances, overtime and labor attraction incentives, and higher fees for faster delivery. Combined with surging demand and supply chain strain, he said, these factors drive costs higher.
Power remains a major hurdle: 56% of those surveyed globally called it a major obstacle to delivery. Just over half said utility connections typically take one to two years, while nearly a third reported waits of more than two years. Power costs vary by region, from $15.01 per watt in Silicon Valley to $10.51 per watt in Dallas, based on a typical 60-megawatt design.
Labor is another headwind, with just over a quarter of respondents saying contractor capacity was sufficient. Barry expects cost increases to moderate to the 6% to 10% range next year, since many major projects are already underway and cost risk has been written into contracts. "I think we've hit a big surge in 2026," he said, especially in new major projects that have been procured.
Source: CNBC